Henwood Rd & Mountain Rd Reservoirs - Civil Works & Reservoir Structures

Client: New Plymouth District Council 

Completion Date: August 2021

 

The project involved building two 4,500 m3 pre-stressed concrete reservoirs at two different sites, including site works and water containment testing.

 

Each tank required the lift and install of fifty-four 8m high panels. This work element involved a significant amount of planning and coordination across several parties. Six to eight panels were installed per day with plus/minus 3mm tolerance.